    Following 1999 floods, the flood protection dike had to be strenghtened, what also required a relocation of the Gennach. The river development was carried out under consideration of ecological aspects with changing river bed widths and slope inclinations. The right bank was not fortified, so a natural watercourse can develop again through self dynamic processes. This will create diverse habitats for flora and fauna. Access to the river was created for the population. 800 woods were planted as noise and sight protection against the neighboring road B 12. 

    Technical characteristics

    400 m restoration of the Gennach, Planting of 800 woods

    Location Latitude
    48.0142000000
    Location Longitude
    10.7203000000
    Comment on location

    Lindenberg, city of Buchloe

    Keywords
    Ecosystem (s) impacted
    Riverfront
    Hazard(s) concerned
    Floods
    Other challenges
    Biodiversity
    Exposition
    Exposed assets
    Urban settings
    Is there population exposed?
    Yes, high density of population (>200 persons/km2)
    Activity
    Are there jobs created in the nature-based sector?
    Don't know
    Are there new employments in tourism sector, sport activities or recreational activites ?
    Don't know
    Are there new activities in the tourism sector , sport activities or recreational activites?
    Don't know
    Are there new/traditional activities that increased?
    I don't know
    International classification
    Sustainable development goals addressed
    SDG 9 – Industry, Innovation and Infrastructure
    Sendai Frameword priorities addressed
    Priority 3. Investing in disaster risk reduction for resilience
    Actors
    Who are the beneficiaries of the action
    inhabitants of Lindenberg
    Temporal aspects
    Design life time of the action
    More than 10 years
    Implementation time of the action
    Less than 2 years
    Financial aspects
    Financing source
    Freistaat Bayern, Municipality of Buchloe
    Others
    Participatory process
    No
    Is it possible to transpose this action in a different context?
    No, it is site specific
    Risk reduction
    Hazard
    0
    Exposure
    +
    Vulnerability
    +
    Feasibility
    Technical Feasibility
    NA
    Economic Feasibility
    NA
    Environment
    Water
    0
    Soil
    0
    Vegetation
    +
    Landscape
    +
    Biodiversity
    +
    Society
    Quality of Life
    +
    Community involvement
    NA
    Landscape Heritage
    NA
    Economy
    Revitalization
    NA
    Local Economy
    NA
    96000.00